Construction Begins on CSAH 10 west of Gaylord June 12th

 

CONSTRUCTION UPDATE I

2019 CSAH 5 & CSAH 10 Resurfacing

PROJECT NO. CP 1213 & CP 1223

CONTRACTOR: OMG MIDWEST, DBA CHARD TILING OF

BELLE PLAINE, MN

This "CONSTRUCTION UPDATE" will provide construction progress for the 2019 Resurfacing Projects and the events that will occur during construction.

PROJECT LOCATION AND DESCRIPTION

On CSAH 5 from CSAH 6 to the north County line. Milling, CIR, Bituminous Overlay, Curb & Gutter Work and Aggregate Shouldering.

On CSAH 10 from CSAH 26 to the City of Gaylord. Milling, Stabilized Full Depth Reclamation, Bituminous Overlay and Aggregate Shouldering.

PROJECT SCHEDULE

Construction will begin on CSAH 10 June 12, 2019. Road will be closed to traffic during construction.

Pipe Replacement Operations – June 12- June 14th

Milling Operations – June 17th – June 21th

FDR Operations – June 24- June 28th

Bituminous – July 8 - July 19th

Striping – July 22- July 26th

CSAH 10 will be closed to thru traffic.

As always, this schedule may need adjustment as time passes due to unpredictable weather, contractor scheduling and other unforeseeable circumstances.

„«

Please visit the Sibley County Public Works website at www.co.sibley.mn.us for the latest information for this project.

„«

Questions/Concerns? Project Manager: Daren Barfknecht – (507) 381-2385 OR CSAH_10_Construction_Update_6.12.2019 Sibley County Public Works – (507) 237-4092

We realize that this construction project may impose some inconveniences. We appreciate your patience and understanding.